NOTICE: Dredging of Lake Worth Inlet
• The dredge Atchafalaya arrived at the Port on Wednesday, January 26.
• The contractor assigned to the project is Cashman Dredging and Marine Contracting Co., LLC.
• Cashman owns the dredge Atchafalaya, which is the expected plant to accomplish the work in the channel and settling basins.
• The dredging depth is set for 39 feet plus two allowable over dredge for outer channel, 37 feet plus two allowable over dredge for inner channel and 33 feet plus two feet allowable over dredge in the turning basin.
• The volume of sand to be removed is approximately 400,000 cubic yards.
• The sand will be placed on the shores of the Town of Palm Beach, at no cost to the residents of Palm Beach.
• Noise levels will be slightly elevated in the area, as operations continue 24 hours a day.
• Mariners are urged to transit at their slowest safe speed to minimize wake and proceed with caution when navigating through the inlet.
• The project duration is estimated to take up to three months.
• The project will ensure the inlet remains accessible to Port tenants who are moving all types of cargo including sugar, molasses, asphalt, diesel fuel and essential goods primarily bound for the Caribbean islands.
• Port of Palm Beach operations support $304 million in local and state business revenue while providing about 2,800 direct jobs.
• This project was awarded with all alternates creating a $10.9 million dollar project for the port with 100% funded by the Federal Government.
• For more information contact the Port of Palm Beach Engineer Ronald Coddington at 561-383-4133.